Stacker Motor Operation Test

To perform the Stacker Motor Operation Test without
the Cash Box, proceed as follows:
1. Remove electrical power.
2. Remove the Cash Box.
NOTE: Be sure to remove the Cash Box
to avoid the risk of damage.
3. Set the DIP Switches as below (Figure 6-121).
Figure 6-121 Stacker Motor Operation Test 1
DIP Switches #1, #3, #8 ON
ON
1
2
3
Figure 6-121 Stacker Motor Operation Test 1
4. Apply electrical power.
5. Confirm that the
lit.
Figure 6-122 St
Figure 6-122 Stacker Motor Operation Test 2
6. To start the Test, set the DIP Switch #8 to
(Figure 6-123).
Figure 6-123 Stacker
DIP Switch #8 OFF
ON
1
2
3
Figure 6-123 Stacker Motor Operation Test 3
7. The Stack Gear will start spinning when the
Stacker Motor functions properly.
Figure 6-124 Stacker Motor Operation Test 4
Figure 6-124 Stacker Motor Operation Test 4
8. Set the UBA Pro DIP Switch #8 to
test.
P/N 960-000211R_Rev. A
UBA™ Pro Series Universal Banknote Acceptor
4
5
6
7
8
Green
and
Red
Status LEDs are
Green Red
OFF
4
5
6
7
8
Stack Gear
to end the
ON
Entrance Motor Operation Test (For-
ward)
To perform the Entrance Motor Operation Test in the
forward rotation, proceed as follows:
1. Remove electrical power.
2. Set the DIP Switches as below (Figure 6-125).
Figure 6-125 Entrance Motor Operation Test
DIP Switches #6, #8 ON
(Forward) 1
ON
1
2
3
Figure 6-125 Entrance Motor Operation Test
(Forward) 1
3. Apply electrical power.
4. Confirm that the
lit.
Figure 6-126 E
Figure 6-126 Entrance Motor Operation Test
(Forward) 2
5. Lift up on the Upper Guide Access Lever to open
the UBA Pro's Cover
6. To start the Test, set the DIP Switch #8 to
(Figure 6-127).
Figure 6-127 Entrance Motor Operation Test
DIP Switch #8 OFF
(Forward) 3
ON
1
2
3
Figure 6-127 Entrance Motor Operation Test
(Forward) 3
7. The Rollers will start running in the forward
direction when the Feed Motor functions prop-
erly.
Figure 6-128 Entrance Motor
Figure 6-128 Entrance Motor Operation Test
(Forward) 4
8. Set the UBA Pro DIP Switch #8 to
test.
© 2020, JAPAN CASH MACHINE CO., LTD.
6 - 2 4
Calibration and Testing
4
5
6
7
8
Green
and
Red
Status LEDs are
Green Red
OFF
4
5
6
7
8
to end the
ON

Advertisement

Table of Contents
loading

Table of Contents