Aging Test With Cash Box; Dip Switch Test - JCM GLOBAL UBA Pro Series Operation And Maintenance Manual

Universal banknote acceptor
Table of Contents

Advertisement

Calibration and Testing
Sensor/
Mechanism
(1) DIP Switch #2 ON
ON
PB_IN
&
(2) Open the Cover.
PB_OUT
(3) Cover the Sensor with a Banknote
(4) Close the Cover firmly.
(5) Confirm that the Status LED is lit as
below when the Sensor detects the
Banknote:
PB IN Sensor:
PB OUT Sensor:
(1) DIP Switch #3 ON
ON
(2) Open the Cover.
(3) Move the PB Guide with your finger.
PB Home
(4) Confirm that the
&
(5) Move the Centering Mechanism with your
Centering Home
fingers.
(6) Confirm that the
are lit.
Centering
Mechanism
(1) DIP Switch #5 ON
ON
Pusher Home
&
Box Exist
(2) Remove the Cash Box.
(3) Reach to and push each "Arm" linked to
the Sensors on the bottom of the Unit.
(4) Confirm that the Status LED is lit as
below when the Sensor turns on:
Pusher Home Sensor:
Box Exist Sensor:
(1) DIP Switch #6 ON
ON
Exit
(2) Remove the Cash Box.
(3) Insert a Banknote from the bottom of the
Unit.
(4) Confirm that the
7. Set the UBA Pro DIP Switch #8 to
test.
P/N 960-000211R_Rev. A
UBA™ Pro Series Universal Banknote Acceptor
Procedure and Confirmation
1
2
3
4
5
6
7
Green
LED
Red
LED
1
2
3
4
5
6
7
Green
LED is lit.
Orange
and
Red
PB Guide
1
2
3
4
5
6
7
Green
LED
Red
LED
1
2
3
4
5
6
7
Green
LED is lit.
to end the
ON

Aging Test with Cash Box

To perform the Aging Test with the Cash Box, pro-
ceed as follows:
1. Remove electrical power.
2. Set the DIP Switches as below (Figure 6-100).
Figure 6-100 Aging Test with Cash Box 1
DIP Switches #4, #8 ON
8
ON
1
Figure 6-100 Aging Test with Cash Box 1
3. Ensure that the Cash Box is properly installed.
4. Apply electrical power.
5. Confirm that the
lit.
8
Figure 6-101 Aging Test with Cash Box 2
LEDs
6. To start the Test, set the DIP Switch #8 to
(Figure 6-102).
Figure 6-102 Aging
DIP Switch #8 OFF
ON
1
Figure 6-102 Aging Test with Cash Box 3
7. The aging operation will begin.
8
8. Set the UBA Pro DIP Switch #8 to
test.

DIP Switch Test

To perform the DIP Switch Test, proceed as fol-
lows:
1. Remove electrical power.
2. Set the DIP Switches as below (Figure 6-103).
Figure 6-103 DIP Switch Test 1
DIP Switches All ON
8
ON
1
Figure 6-103 DIP Switch Test 1
6 - 2 1
2
3
4
5
6
Green
and
Red
Status LEDs are
Figure 6-101 A
Green Red
2
3
4
5
6
ON
2
3
4
5
6
© 2020, JAPAN CASH MACHINE CO., LTD.
Section 6
7
8
OFF
7
8
to end the
7
8

Advertisement

Table of Contents
loading