Commissioning instructions

Installing a replacement MCB in an older Vigilon Compact panel

These instructions cover how to fit a replacement Master Control Board (VCS-MCB-N) into a COMPACT-24-N
(networkable) or COMPACT-24 (non networkable) Vigilon Compact panel.
Replacement Master Control Board (MCB)
- networkable
NC C NO NC C NO NC C NO
24V
0V
B
A
TX1 RX1 0V
TX2 RX2
L1 0V L2 0V
L1 0V L2 0V
0V MIPNC C NO
PB15
PB6
PB14
PB10
PB11
PB7
PB9
24V
MA1 - FS1 250mA
FS3 200mA
MA2 - FS2 250mA
P1
CARD 2
P2
CARD 1
FIRMWARE BACKUP
IC3
IC16
SW2
MODE
P16
SW1
RESET
Insulation Disk
&
- When a network card is fitted onto the MCB, ensure a spade tab (supplied) is fitted under
the PCB fixing screw at position u.
- Also ensure the bottom PCB fixing screw v is tightened to give good electrical connection.
How to replace the MCB
There are in existence four variants of Vigilon Compact panels in the field. Here are the steps to replace an MCB
fitted in a Vigilon Compact panel.
Save Configuration to Commissioning tool
¨
If the panel is functioning correctly then before powering down ensure the system configuration is
retrieved using the commissioning tool.
Power down
¨
Completely power down the panel by isolating the mains and battery supply and then remove the
ribbon cable connectors from the MCB.
36
OLD Master Control Board (MCB)
- non networkable
MA1+ MA1- MA2+ MA2-
PB8
P15
P10
P11
P6
24V
FS3 200mA
P1
CARD 2
BATT1
CODE
BCKUP
POWER
SUPPLY
P12
IC3
IC16
P16
BATT3
Remove the cards
¨
Remove the Loop card(s) and Network card# from the MCB and then
remove the MCB from the panel. (# - where applicable)
Select the firmware part number and set the rotary switch
¨
Make a note of the firmware number on the chip in socket IC3 of the
MCB being replaced. Determine the applicable switch setting
required from the table below and set the rotary switch on the
P14
P7
P9 P8
replacement MCB.
MA2 - FS2 250mA
MA1 - FS1 250mA
P2
CARD 1
The firmware in socket
IC3 of MCB being
replaced
2211-148
2211-146
2211-136
POWER
SUPPLY
2211-127
P12
Re-fit the cards
SW1
P13
¨
Fit the replacement MCB into the panel and reconnect the ribbon
cables, and then fit the previously removed Network and Loop cards.
¨
An earth lead must be fitted between the spade tabs
Network card.
Configuration
¨
Using a chip extractor extract the back up 'Configuration' chip fitted
in socket IC16 (NVM) of the MCB being replaced and fit this chip
into the replacement MCB.
&
is incompatible then DO NOT fit the chip into the replacement
MCB. Instead transmit the saved configuration from the
commissioning tool to the replacement MCB. The transmission
must take place after panel power up. After transmitting the
configuration to the panel 'back up' the data to NVM on Card 14.
Power up
¨
Power up the mains and battery supplies to the panel.
Applicable setting of switch
SW2 on replacement MCB
0
1
2
3
Where the Configuration chip is known to be corrupt or
4188-856_issue 7_07/15_Generic Vigilon (Compact + VA) Comms.
u
on MCB and