Commissioning instructions

A typical commissioning process

Always power-down the panel when
for example when wiring or replacing parts
Pre visit checks
Ensure you have:
As-fitted-drawings that
shows installed system equipment
Access will be available to protected areas having system equipment
Installer will be present to rectify wiring faults
Tools and spare parts are available.
Inform responsible person(s)
Inform responsible person(s) that the fire alarm system is being
commissioned and occupants in the protected premises will hear
test alarms.
Ensure occupants are made aware of alternative site procedures
should there be a fire event while the system is commissioned.
Survey the installation
Refer to the most recent
as-fitted-drawings
system equipment has been installed in accordance with the
installation instructions, respective standards and project specification.
Before powering up the Panel
Open the outer cover and inner cover of the panel and:
– Check all the internal cables within the enclosure are securely fitted
– Fit the loop card(s) into the required location(s)
– Ensure no external circuits are connected at this stage, except for
the mains supply which must be connected but not switched ON
Fit the
end of line
resistors to the master alarm circuits.
– Connect the external printer to the RS232 port, if required.
– Ensure the input - output lines of interface units on the loop are not
connected.
Power up
– Fit the batteries inside the panel enclosure and connect the battery
leads and then switch ON the mains supply.
8
working on the system,
.
and ensure that all the fire
Initial tests and set ups
– Setup Access levels PIN codes, if required
– Carry out a display test and ensure DISPLAY and LEDs are working
– Set the system clock time and date
Configure the RS232 printer port, if an external printer is installed.
Loop Devices
Configure the links on all LV 4-channel interface units connected to
the loop. Ensure links are set for either Input or Output application.
Ensure all interface Input/Output external wiring remains
disconnected at this stage, unless otherwise instructed. This
action will prevent inadvertent operation of output/plant while
the system is being commissioned.
– Power up the mains powered interface unit on the loop.
Loop device address allocation
– Connect only End 1 of a loop circuit and power-up the loop
– Allow address allocation to finish. Any fault(s) on the loop during
allocation must be rectified. Power-down the loop when correcting
loop wiring faults and the power-up to continue address allocation
– Connect only End 2 of the loop circuit and power cycle the loop and
ensure address allocation is complete from End 2.
– Connect both End 1 and End 2 of the loop and check the loop
allocation is complete with both ends of the loop connected.
– 'Starting Loop n' displayed after successful allocation of addresses.
– Check all the devices on the loop circuit are installed in their correct
location using the '
Find Device
' function at the panel and by referring
to the '
as fitted wiring drawings
'
– Check to ensure correct devices are installed by viewing the
'Device status'
– Repeat the allocation process on other loop circuits.
Pre-allocate the wireless devices
– If the system has wireless devices then pre-allocate the
wireless devices and bind them to the respective LRT.
Then allocate loop again to allow panel to see the devices.
Continue on next page
4188-856_issue 7_07/15_Generic Vigilon (Compact + VA) Comms.

Advertisement

Table of Contents
loading

This manual is also suitable for:

Vigilon 6 loopVigilon compactVigilon compact va

Table of Contents