5) Install cylinder head to block.
After applying oil to cylinder head bolts, tighten them gradu-
ally as follows.
a) Tighten all bolts to 53 N·m (5.3 kg-m, 38.5 lb-ft) according
to numerical order in the figure.
b) In the same manner as in a), tighten them to 84 N·m (8.4
kg-m, 61.0 lb-ft).
c) Loosen all bolts until tightening torque is reduced to 0 in
reverse order of tightening.
d) In the same manner as in a), tighten them to 53 N·m (5.3
kg-m, 38.5 lb-ft).
e) In the same manner as in a) again, tighten them to speci-
fied torque.
Tightening torque
Cylinder head bolt (a) : 105 N·m (10.5 kg-m, 76.0 lb-ft)
Cylinder head bolt (hex hole bolt) (b) :
11 N·m (1.1 kg-m, 7.5 lb-ft)
NOTE:
Don't forget to install (b) bolts as shown in the figure.
1. Hex hole bolt
2. Crankshaft pulley side
3. Flywheel side
[A] RH bank
[B] LH bank
6) Install water outlet cap.
7) Check timing mark on crankshaft as shown in the figure.
1. Crank timing pulley key
2. Oil jet
8) Install valve lash adjuster, camshaft, CMP sensor and RH
bank 2nd timing chain.
Refer to "CAMSHAFT AND VALVE LASH ADJUSTER" and
"RH (NO.2) BANK 2ND TIMING CHAIN AND CHAIN TEN-
SIONER" in this section. For CMP sensor, refer to "CMP
SENSOR" in Section 6F2.
9) Install 1st timing chain.
Refer to "1ST TIMING CHAIN AND CHAIN TENSIONER" in
this section.
10) Install LH bank 2nd timing chain.
Refer to "LH (NO.1) BANK 2ND TIMING CHAIN AND CHAIN
TENSIONER" in this section.
11) Install timing chain cover.
Refer to "TIMING CHAIN COVER" in this section.