Installation Location Requirements

Short Gas Paths
Adequate Air
Circulation
Protection from
Adverse Conditions
Environmental
Conditions
42/24-10 EN Rev. 9

Preparing the Installation

Install the gas analyzer as close as possible to the sampling location.
Locate the gas preparation and calibration assemblies as close as possible to the
gas analyzer.
Provide for adequate natural air circulation around the gas analyzer. Avoid heat
buildup.
When installing several system housings in a 19-inch rack, maintain a minimum
spacing of 1 rack unit between housings.
The entire surface of the system housing is used to dissipate heat.
Protect the gas analyzer from:
• Cold
• Direct sunlight and heat
• Large temperature variations
• Strong air currents
• Accumulations of dust and dust infiltration
• Corrosive atmospheres
• Vibration (see "Vibrations", page 1-2)
Air pressure range
Relative humidity
Ambient temperature range at storage and transport
Ambient temperature range during operation with
analyzer module
installed in a system housing
without electronics module
Caldos25
+5 to +45°C
Caldos27
+5 to +50°C
Limas11
+5 to +45°C
Magnos206
+5 to +50°C
Magnos27
+5 to +45°C
Uras26
+5 to +45°C
Oxygen Sensor
+5 to +40°C
1) +5 to +40°C when I/O modules are installed
2) +5 to +50°C for measurement chamber direct connection and installation in
system housing without electronics module or Uras26
Chapter 1: Preparing the Installation
installed in a system housing
with electronics module or
with power supply only
+5 to +45°C
+5 to +45°C
+5 to +45°C
+5 to +45°C
2)
+5 to +45°C
+5 to +40°C
+5 to +40°C
600 to 1250 hPa
max. 75 %
–25 to +65 °C
1)
Continued on next page
1-1