Oracle sparc M5-32 Installation Manual page 31

Table of Contents

Advertisement

Requirement
Question
Are there enough power outlets available to power the server and peripherals?
See
"Facility Power Receptacles" on page 36
Have you prepared two facility power grids to power the server?
See:
"Facility Power Requirements" on page 37
"Power Cord-to-Power Supply Relationship" on page 40
Have you prepared the appropriate facility power outlets for the power cords? Are
all of these outlets grounded?
See:
"Power Cord Specifications" on page 32
"Grounding Requirements" on page 42
Are there circuit breakers for each power cord and do they meet the capacity
requirements?
See
"Circuit Breaker Capacity Requirements" on page
Operating
Does the data center meet the temperature and humidity requirements?
environment
See
"Environmental Requirements" on page
and cooling
Does the installation site environment provide adequate ventilation and airflow to
cool an operating server?
See:
"Heat Dissipation and Airflow Requirements" on page 47
"Cooling Airflow From Ceiling Vents" on page 49
"Cooling Airflow From Perforated Floor Tiles" on page 50
Have you taken measures to prevent airborne contaminates from entering the
installation site?
See
"Airborne Contaminates" on page
Unpacking
Have you acclimated the packaged server to the data center environment prior to
unpacking it?
See
"Loading Dock and Receiving Area Requirements" on page
and your peripheral documentation.
43.
44.
45.
Check
55.
Preparing the Site
21

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sparc m6-32

Table of Contents