IBM Multiprise 3000 S/390 Installation Manual page 56

Enterprise
Table of Contents

Advertisement

2 IBF Power switches
1. If installed insure that the breaker switch of
each IBF (Integrated Battery Feature) is in
the On position.
Note: The location of the IBF's are directly
to the left of the DASD at the front
of the frame.
2. Repeat this step for each frame.
3 Setting EPO switches
1. At the front of each frame, set the red
Unit Emergency Only switch to the ON
position (|).
2. Repeat this step for each frame.
4-6