Sequence When Creating Drive Components - Siemens SINAMICS S120 Commissioning Manual

With startdrive
Hide thumbs Also See for SINAMICS S120:
Table of Contents

Advertisement

Commissioning
5.3 Creating a project offline
This information is generated and administered in the user administration of the TIA Portal. You
can find further information about project protection in the Startdrive information system under
"Using user administration".
5.3.3

Sequence when creating drive components

Overview
As a rule, the needed components must be inserted into the device configuration and specified
after a new project is created. If the recommended sequence is maintained when inserting the
components, then the inserted components are also automatically wired.
Recommended order
We recommend the drive components be inserted in the following order:
1. Control Unit
2. Infeed unit
3. Motor Module or Power Module
4. Motor
5. Encoders or measuring systems
6. Supplementary system components (e.g.: Terminal Module, Terminal Board,
Communication Board, Voltage Sensing Module)
If this sequence is not complied with (e.g. because the infeed unit is only subsequently added),
then it is possible that the components are not automatically wired. In this case, you must
manually establish the wiring in the device view (see Chapter "Editing DRIVE-CLiQ connections
(Page 117)").
Note
For some motors, an appropriate encoder is simultaneously created in the device view when
creating and specifying a motor. The corresponding encoder is specified together with the
motor.
Note
When you use Power Modules, it is usually possible to dispense with an infeed unit. Point 2 in the
list above is then no longer applicable.
102
Commissioning with Startdrive
Commissioning Manual, 06/2020, 6SL3097-5AA10-0BP2