12.3.4.2
Selección de la curva de actuación (t4)
Se pueden seleccionar 4 curvas de actuación diferentes mediante los dip-
switch indicados en la fig. 48 ref. L.
Dichas curvas se definen:
– Curva A - tiempo de actuación 100ms con sobrecarga mínima de
3.25 x I4
- con sobrecarga inferior a 3.25 x I4 la curva es I²t = Cost
(100ms a 3.25 x I4)
– Curva B - tiempo de actuación 200ms con sobrecarga mínima de
2.25 x I4
- con sobrecarga inferior a 2.25 x I4 la curva es I²t = Cost
(200ms a 2.25 x I4)
– Curva C - tiempo de actuación 400ms con sobrecarga mínima de 1.6
x I4
- con sobrecarga inferior a 1.6 x I4 la curva es I²t = Cost
(400ms a 1.6 x I4)
– Curva D - tiempo de actuación 800ms con sobrecarga mínima de
1.25 x I4
- con sobrecarga inferior a 1.25 x I4 la curva es I²t = Cost
(800ms a 1.25 x I4)
La tolerancia en los tiempos de actuación es ± 20%.
En la siguiente tabla se indican las programaciones posibles:
Curva/ Curve
Curva/ Curve
12.3.4.3 Ejemplo de programación
A continuación se ilustra un ejemplo de programación de la protección
contra defecto a tierra (G) tomando como referencia el ejemplo de
programación 12.3.3.3.
Se desea efectuar una protección con las siguientes características:
Un interruptor SACE Emax con TA de 2000A y una corriente nominal
de circulación de 925A.
Se desea proteger la carga de la manera siguiente:
– en un tiempo de 25s con una sobrecarga 5 veces superior a la corriente
de circulación
– en un tiempo de 500ms con una sobrecarga 9 veces superior a la
corriente de circulación
– en un tiempo de 35ms con una sobrecarga 13 veces superior a la
corriente de circulación
– en un tiempo de 350 ms con sobrecarga de defecto a tierra alcanza un
valor 0.9 veces superior a la corriente de circulación
Cálculo del umbral I1 y de la curva de actuación t1
Véase el ejemplo de programación del párrafo 12.3.1.3.
Cálculo del umbral I2 y de la curva de actuación t2
Véase el ejemplo de programación del párrafo 12.3.2.3.
Cálculo del umbral I3
Véase el ejemplo de programación del párrafo 12.3.3.3.
Cálculo del umbral I4 y de la curva de actuación t4
a) Se calcula la relación entre la corriente de sobrecarga y la corriente
nominal del TA que define el valor del umbral "G" (SG) que se debe
programar:
El valor práctico que se debe programar es / Practical value to be set is SG = 0.4
Mod.
M4379
Rev.
A
B
I = 0.9 x IU = 0.9 x 925 = 832.5A
12.3.4.2
Selection of the trip curve (t4)
4 different trip curves can be selected by using the dip-switches indicated
in fig. 48 ref. L.
These curves are defined as follows:
– Curve A - trip time 100ms with minimum overload of 3.25 x I4
- with overload less than 3.25 x I4 the curve is I²t = Const
(100ms at 3.25 x I4)
– Curve B - trip time 200ms with minimum overload of 2.25 x I4
- with overload less than 2.25 x I4 the curve is I²t = Const
(200ms at 2.25 x I4)
– Curve C - trip time 400ms with minimum overload of 1.6 x I4
- with overload less than 1.6 x I4 the curve is I²t = Const
(400ms at 1.6 x I4)
– Curve D - trip time 800ms with minimum overload of 1.25 x I4
- with overload less than 1.25 x I4 the curve is I²t = Const
(800ms at 1.25 x I4)
The trip time tolerance is ±20%.
The following table shows the possible settings:
Curva/ Curve
C
Curva/ Curve
D
12.3.4.3 Example of setting
An example of setting the protection against earth fault (G) taking a cue
from setting example 12.3.3.3 is given.
A protection with the following characteristics is to be made:
A SACE Emax circuit-breaker mounts 2000A CTs and the rated
circulating current in 925A.
The load is to be protected as follows:
– within a time of 25s with an overload 5 times the circulating current
– within a time of 500ms with an overload 9 times the circulating current
– within a time of 35ms with an overload 13 times the circulating current.
– within a time of 350ms with earth fault overload, it reaches the value of
0.9 times the circulating current.
Calculation of the threshold I1 and of trip curve t1
See setting example 12.3.1.3.
Calculation of threshold I2 and trip curve t2
See setting example 12.3.2.3.
Calculation of threshold I3
See setting example 12.3.3.3.
Calculation of threshold I4 and trip curve t4
a) The relationship between the overload current and the rated current of
the CT is calculated which defines the value of threshold "G" (SG) to
be set:
SG = I / In = 832.5 / 2000 = 0.41625
Aparato
Apparatus
N° Doc.
Doc. No.
SACE Emax
601933/003
Escala
Scale
N° Pag.
Sh. No.
59/100