Power supply unit UPS (77 3400 00)
6.1.4
Commissioning
1. Activate the UPS function at control terminals x + y (3).
The device is activated for UPS operation at control terminals "x" and "y" (3).
To activate the UPS function, attach the 7-pole terminal (2) provided together
with the insertion bridge (3), or close control terminals "x" and "y" using a po-
tential-free normally open contact.
-
The UPS function is now activated. Note: The UPS function is not ready until
the mains voltage has been switched on at least once. The current through
the insertion bridge is approximately 1 mA in this case.
2. Switch on the mains voltage.
Once all the connections have been established as described and the UPS func-
tion has been activated, switch on the mains voltage:
Switch on the mains voltage.
-
A voltage of 24 V DC is at the connections. The green "Output +24V DC"
LED (1) lights up when there is voltage at the output.
-
The power supply unit UPS is in operation.
3. Test the UPS function.
The UPS function is ready when the mains voltage has been switched on at least
once. Perform a functional test:
Switch off the mains voltage.
-
The connected nurse call system is supplied by the batteries until the mains
voltage is switched on or until the total discharge protection disconnection
function is activated.
-
The yellow "Battery active" LED (1) lights up.
Switch the mains voltage back on.
Power supply unit UPS (77 3400 00) – Instruction manual – 00 8802 41, 04/16 (Rev. 9.0)
Connections and commissioning