:INTEGrate:RTALl:{STARt|END}
Function
Collectively sets the integration start or end time
of all elements for real-time integration mode.
:INTEGrate:RTALl:{STARt|END} {<NRf>,
Syntax
<NRf>,<NRf>,<NRf>,<NRf>,<NRf>}
{<NRf>,<NRf>,<NRf>,<NRf>,<NRf>,<NRf>} =
2001,1,1,0,0,0 to 2099,12,31,23,59,59
First <NRf> = 2001 to 2099 (year)
Second <NRf> = 1 to 12 (month)
Third <NRf> = 1 to 31 (day)
Fourth <NRf> = 0 to 23 (hour)
Fifth <NRf> = 0 to 59 (minute)
Sixth <NRf> = 0 to 59 (second)
:INTEGRATE:RTALL:START 2018,1,1,0,
Example
0,0
:INTEGrate:RTIMe<x>?
Function
Queries the integration start and end times for
real-time integration mode.
:INTEGrate:RTIMe<x>?
Syntax
<x> = 1 to 7 (element)
:INTEGrate:RTIMe<x>:{STARt|END}
Function
Sets or queries the integration start or end time
for real-time integration mode.
Syntax
:INTEGrate:RTIMe<x>:{STARt|
END} {<NRf>,<NRf>,<NRf>,<NRf>,<NRf>,
<NRf>}
:INTEGrate:RTIMe<x>:{STARt|END}?
<x> = 1 to 7 (element)
{<NRf>,<NRf>,<NRf>,<NRf>,<NRf>,<NRf>} =
2001,1,1,0,0,0 to 2099,12,31,23,59,59
First <NRf> = 2001 to 2099 (year)
Second <NRf> = 1 to 12 (month)
Third <NRf> = 1 to 31 (day)
Fourth <NRf> = 0 to 23 (hour)
Fifth <NRf> = 0 to 59 (minute)
Sixth <NRf> = 0 to 59 (second)
Example
:INTEGRATE:RTIME1:START 2018,1,1,0,
0,0
:INTEGRATE:RTIME1:START?
-> :INTEGRATE:RTIME1:START 2018,1,1,
0,0,0
Description • This command is valid when the integration
mode (:INTEGrate:MODE) is set to real-time
integration mode (RNORmal or RCONtinuous).
• When independent element integration
(:INTEGrate:INDependent) is set to OFF (0),
you can omit <x> (<x> = 1). The operation is
performed on all elements using element 1's
integration start or end time.
IM WT5000-17EN
:INTEGrate:STARt
Function
Starts integration.
:INTEGrate:STARt {[<NRf>][,<NRf>]
Syntax
[,<NRf>][,<NRf>][,<NRf>][,<NRf>]
[,<NRf>]}
<NRf> = 1 to 7 (element)
:INTEGRATE:START (starts integration on all
Example
elements)
:INTEGRATE:START 1,2,3 (starts integration
on the specified elements)
Description • When independent element integration
(:INTEGrate:INDependent) is set to ON (1),
you can use the parameters to specify which
elements to perform the operation on. If you
omit the parameters, the operation will be
performed on all the elements.
• When independent element integration
(:INTEGrate:INDependent) is set to OFF (0),
you cannot use the parameters to specify
elements.
:INTEGrate:STATe?
Function
Queries the integration status.
:INTEGrate:STATe? {<NRf>}
Syntax
:INTEGrate:STATe?
<NRf> = 1 to 7 (element)
Example
• When independent element integration
(:INTEGrate:INDependent) is set to OFF (0):
:INTEGRATE:STATE? -> RESET
• When independent element integration
(:INTEGrate:INDependent) is set to ON (1):
:INTEGRATE:STATE? 1 -> RESET
:INTEGRATE:STATE?
-> RESET,RESET,RESET,RESET,RESET,
RESET,RESET
Description • The response is as follows:
RESet = Integration reset
READy = Waiting (real-time integration mode)
STARt = Integration in progress
STOP = Integration stop
ERRor = Abnormal integration termination
(integration overflow, power failure)
TIMeup = Integration stop due to integration
timeout
• When independent element integration
(:INTEGrate:INDependent) is set to OFF (0),
you cannot use the parameter to specify the
element that you want to query.
• When independent element integration
(:INTEGrate:INDependent) is set to ON (1), you
can use the parameter to specify the element.
If the parameter is omitted, the integration
statuses of all elements are output in order,
starting with element 1.