Installing the Radiator and Hydraulic Fluid Cooler (continued)
Outcross 9060
18234SL Rev B
5. Secure the fuel cooler assembly to the hydraulic fluid cooler.
6. Remove the covers and plugs from the openings in the radiator and the
hydraulic fluid cooler and the disconnected coolant and hydraulic lines that
were installed during removal.
7. Connect the hydraulic lines to the hydraulic fluid cooler.
8. Connect the upper and lower radiator hoses and the reservoir hose to the
radiator and secure the hoses with the hose clamps.
9.
Fill the reservoir with coolant; refer to the traction unit Operator's Manual.
10. Add hydraulic fluid to the hydraulic reservoir as necessary; refer to the
traction unit Operator's Manual.
11. Start the engine and check for coolant and hydraulic fluid leaks. Repair any
leaks as required.
12. Continue to run the engine to obtain the operating temperature. Check the
coolant and hydraulic fluid levels and adjust as necessary before returning
the machine to service.
13. Install the front screen.
Page 4–13
Engine: Service and Repairs