Installing the Front Loader Control Valve
Outcross 9060
18234SL Rev B
1. Lubricate new O-rings and place them onto the fittings. If previously removed,
install the fittings into the valve ports; refer to
(SAE Straight Thread O-Ring Fittings) (page
2. Secure the valve assembly to the machine with 4 cap screws.
3. Remove the caps and plugs from the fittings and hydraulic lines and connect
the hydraulic lines to the valve; refer to
(O-Ring Face Seal) (page
4. Operate the front loader control valve. Check for hydraulic leaks and correct
if necessary.
5. Install the operator's console; refer to
Console (page
8–17).
6. Check the hydraulic fluid level and adjust if necessary before returning the
machine to service.