Functions
8.5 Setpoint calculation
Table 8- 10
Parameter
p1138
p1139
Example
In the following example, the higher-level control sets the ramp-up and ramp-down times of
the inverter via PROFIBUS.
Figure 8-16
Preconditions
● You have commissioned the communication between the inverter and the control system.
● Free telegram 999 has been set in the inverter and in your higher-level control system.
See also section: Extend telegrams and change signal interconnection (Page 139).
● The controller sends the scaling value to the inverter in PZD 3.
Procedure
To interconnect the scaling of the ramp-up and ramp-down times with PZD receive word 3
from the fieldbus in the inverter, proceed as follows:
1. Set p1138 = 2050[2].
This means that you have interconnected the scaling factor for the ramp-up time with
PZD receive word 3.
2. Set p1139 = 2050[2].
This means that you have interconnected the scaling factor for the ramp-down time with
PZD receive word 3.
The inverter receives the value for scaling the ramp-up and ramp-down times via PZD
receive word 3.
You will find further information in the Internet at: Function Manual
(https://support.industry.siemens.com/cs/gb/en/view/60467055/29243398027).
180
Parameters for setting the scaling
Description
Up ramp scaling (factory setting: 1)
Signal source for scaling the acceleration ramp.
Down ramp scaling (factory setting: 1)
Signal source for scaling the deceleration ramp.
Example for changing the ramp-function generator times in operation
SINAMICS G110M Operating Instructions
Operating Instructions, 04/2015, FW V4.7.3, A5E31298649B AD

Advertisement

Table of Contents
loading

Table of Contents