Commissioning
5.2 Basic commissioning
Procedure without application class or for the application class [0]: Expert
2.
3.
4.
5.
6.
7.
8.
110
Select the re-
quired function
modules for your
application.
Select the control
mode.
Select the I/O configuration to preassign the inverter interfaces.
The possible configurations are listed in Sections: Optimizing the speed
controller (Page 189) and V/f control (Page 182).
Set the applicable motor standard and the inverter supply voltage.
Select the application for the inverter:
• "[0] Load cycle with high overload for applications requiring a high
dynamic performance, e.g. conveyor systems.
• "[1] Load cycle with low overload ..." for applications that do not
require a high dynamic performance, e.g. pumps or fans.
• [6], [7]: Load cycles for applications with encoderless 1FK7
synchronous motors.
Select your motor.
Enter the motor data according to the rating plate of your motor.
If you have selected a motor based on its article number, the data has
already been entered.
Set the most important parameters to suit your application.
Technological use:
• [0]: In all applications that do not fall under [1] ... [3]
• [1]: Applications involving pumps and fans
• [2]: Applications with short ramp-up and ramp-down times. However,
this setting is not suitable for hoisting gear and cranes/lifting gear.
• [3]: Setting only for steady-state operation with slow speed changes.
We recommend setting [1] if load surges in operation cannot be
ruled out.