Dielectric strength (hi-pot) test equipment
•
AC female line cord (to create test cable)
•
AC male line cord (to create test cable)
Preparing the lamp power supply for testing
You must prepare the lamp power supply (LPS) before completing the ground continuity and dielectric
strength (hi-post) tests.
1. Disconnect the LPS from its power source.
2. Remove the side cover from the LPS:
a) Loose the bottom three screws.
b) Remove the top three screws.
c) Lift and remove the side cover.
3. Disconnect the two DC output cables from the LPS (see E and F in the diagram).
A
AC convenience outlet
B
AC convenience outlet
C
Three-phase AC input opening
D
AC input terminal block
E
DC output cable opening
F
DC output cable opening
Roadie 4K35 and 4K45 Service Manual
020-101694-03 Rev. 1 (01-2016)
Copyright
2016 Christie Digital Systems USA Inc. All rights reserved.
©
Parts and module replacement
83