12.3 Loading a Patch

Patches can be loaded through FTP, TFTP, or XModem.

12.3.1 Establishing the Configuration Task

Before loading a patch, familiarize yourself with the applicable environment, complete the pre-
configuration tasks, and obtain the required data. This can help you complete the configuration
task quickly and accurately.
Applicable Environment
Before a patch is installed, it should be uploaded to the root directory of the CF card of the master
and slave MPUs. Upload the patch to the root directory of the CF card of the master MPU. Then,
copy the patch to the root directory of the CF card of the slave MPU.
The three methods to upload a patch are FTP, TFTP and XModem.
Pre-configuration Tasks
Before loading a patch, complete the following tasks:
l
l
Data Preparation
Before running a patch, you need to obtain a patch that is consistent with the board.
No.
1
2
12.3.2 Loading a Patch
On a dual-MPU router, you need to load a patch to both the master MPU and the slave MPU.
Context
Do as follows on the router to be upgraded:
Procedure
Step 1 Upload a patch to the root directory of the CF card of the master MPU.
Issue 02 (2011-09-10)
Ensuring that the router is started normally after power-on
Ensuring that the router can be logged in to
Data
Uploading a Patch to the Root Directory of the CF Card of the Master MPU
Copying a Patch to the Root Directory of the CF Card of the Slave MPU
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
12 Patch Management
304

Advertisement

Table of Contents
loading

This manual is also suitable for:

Netengine40e

Table of Contents