Basic hardware procedures
4.7
Switching on the server
V
CAUTION!
Before switching on the server, make sure the top cover is closed. In
●
order to comply with applicable EMC regulations (regulations on
electromagnetic compatibility) and satisfy cooling requirements, the
server must not run while the top cover is removed.
After connecting all power cords, wait at least 60 seconds before
●
pressing the On / Off button.
For further safety information, please refer to chapter
●
information" on page
I
This step is only applicable to replace or expand non-hot plug
components.
Ê Press the On / Off button to start up the server.
Ê Ensure that the power-on indicator above the On / Off button is lit green.
Ê Perform the required procedures described in the concluding steps of each
upgrade or maintenance task.
4.8
Handling riser modules
Removing the riser module 1
Figure 13: Removing the riser module 1
Ê Carefully pull out the riser module 1 upward.
58