6.4.3

Installing the new power supply unit

Ê Install the power supply unit as described in section
supply unit" on page
6.4.4

Concluding steps

"Connecting the server to the mains" on page 57
Ê
Ê Only when replacing a power supply unit in a non-redundant configuration:
"Switching on the server" on page 58
"Performing a fan test after replacing a defective fan" on page 89
Ê
6.5

Replacing the power distribution board

Field Replaceable Unit
(FRU)
Tools: Phillips PH2 / (+) No. 2 screw driver
6.5.1

Preliminary steps

"Locating the defective server" on page 43
Ê
"Disabling BitLocker functionality" on page 63
Ê
"Shutting down the server" on page 46
Ê
"Disconnecting the server from the mains" on page 47
Ê
"Getting access to the component" on page 47
Ê
"Removing the riser module 3" on page 60
Ê
RX200 S8
94.
Upgrade and Maintenance Manual
Power supply
"Installing the power
Hardware: 15 minutes