Procedure
Procedure
1. Insert the front bezel hooks to the chassis (callout 1).
2. Close the front bezel (callout 2).
3. While pressing the key against the lock, rotate the key to the lock position (callout 3).
4. (Optional) For later use, store the front bezel keys inside the front bezel.
Install the server into the rack
Install the server into the rack
Prerequisites
Prerequisites
Get help to lift and stabilize the server during rack installation. If the
might be required to help install the server
might be required to help install the
If the server
server: : One person to support the server weight, and the other to slide the server into the rack.
server is installed higher than chest level, an additional person
is installed higher than chest level, an additional person