Orient the server back in tower mode .
Install the server into the rack .
14. Connect all peripheral cables to the server.
15. Connect each power cord to the server.
16. Connect each power cord to the power source.
17. Power up the server.
Results
Results
The installation is complete.
Installing an expansion card on the tertiary riser
Installing an expansion card on the tertiary riser
Prerequisites
Prerequisites
Make sure that the server is in a dual-processor configuration .
Before you perform this procedure, make sure that you have the following items available:
T-10 Torx screwdriver
Phillips No. 1 screwdriver
About this task
About this task
CAUTION:
CAUTION:
A discharge of static electricity from a finger or other conductor might damage system boards or other static-sensitive
devices. To prevent damage, observe antistatic precautions.
CAUTION: To prevent improper cooling and thermal damage, do not operate the server unless all PCI slots have either
CAUTION:
a riser slot blank or an expansion card installed.
Procedure
Procedure
1. Power down the server.
2. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3. Disconnect all peripheral cables from the server.
4. Do one of the following:
If the server is in tower mode, place the server on a flat, level surface with the access panel facing up .
If the server is in rack mode, remove the server from the rack .
5. Remove the access panel .
6. If installed, remove the boot device.
7. If installed, remove the energy pack:
a. Disconnect the energy pack extention cable from the system board .
b. Press and hold the release latch (callout 1).
c. Lift one end of the energy pack and release it from the holder (callouts 2 and 3).