Figure 1: Preparing and commissioning a safety system that includes the Advanced safety option
Preparing for the commissioning before the first start-up of the system with the option board
1. Read carefully the warnings in chapter Safety of the Advanced safety options Operating
Guide.
2. Read the Advanced safety options Operating Guide and the Commissioning report and
apply their instructions in the commissioning plan.
3. Read the User Manual of the AC drive.
4. Refer to the user manuals of other subsystems connected to the commissioned drive
system.
5. Define the parameter file for the Advanced safety option board.
6. Make sure that the hardware and configuration are correct, and that the software is correct
in the components of the AC drive and its subsystems.
7. Make sure that the information of the commissioned AC drive matches the information in
the commissioning plan and the Commissioning report.
8. Make sure that the connections between different systems have been checked and are
ready to be used.
9. Make sure that the area affected by the commissioned systems is free and secure for the
commissioning.
10. Make sure that no danger can be caused to personnel if the system has been configured
incorrectly and behaves unexpectedly.
11. Make sure that the AC drive is correctly parameterised and commissioned for use.
The motor parameters have been set.
The identification run has been done. Preferred identification type: identification
with run or encoder ID run.
board
VACON
5