Site Preparation

Electrical and Environmental Requirements

Input Voltage
200-240 VAC,
Maximum Power rating 13A,
Typical 600 VA, 50/60 Hz

Connect the DPT Rack and Safety Enclosure to AC Mains

AC Power Cord

A mains power cord, (8121-3445 for N. America only or 8121-3356 for all other
countries) 2.5 m long, Type A, IEC-60320 C19 to Type B Free End) is supplied
with the PD1500A Rack and Safety Enclosure. A qualified electrician must either:
18
10 %,
The Double-Pulse Test Rack and Safety Enclosure is designed to
operate on 200 to 240 VAC single phase. Do not attempt to
operate the DPT Rack and Safety Enclosure on 120VAC.
AC wiring and the Mains Disconnect are subject to local
and regional electrical codes. A licensed electrician must
determine and install the appropriate Mains Disconnect.
Copper wire must be used in the power drop. A licensed
electrician must determine the wire size for the power drop
according to local and regional electrical codes. The wires
must be sized to ensure that the voltage at the system does
not drop below 90% of the nominal voltage.
– permanently hard wire the free end to the AC power source or
– attach an IEC 60309 AC power plug (L+N+P 6h is recommended) to the
cable (a matching IEC 60309 AC Power receptacle must also be installed).
IEC 60309 connectors are not included with the PD1500A system.
LEAKAGE CURRENT! Due to the types of instruments installed in
this cabinet, there is a risk of leakage current (> 3.5 mA). Reliable
ground circuit continuity is required for safe operation of this
product. To reduce the risk of electrical shock, an earth (ground)
connection is essential before connecting the AC power mains.
Never operate the system with the ground connector
disconnected. Use a permanent safety ground connection
(recommended) or a plug meeting the IEC 60309 (CEE plug)
requirements.

Electrical and Environmental Requirements

Operating
Operating Humidity
Temperature
20 °C to +30 °C
50% to 80% RH,
Non-condensing
Keysight Double-Pulse Test System Installation Guide
Operating
Environment
Indoor location only