Installing the unit

7.3. Connection process sequence

Once the unit has been mounted in its final position and has been solidly secured, make the electrical connections
to it. The order is as follows:
1.
Ground connection.
2.
DC connection.
3.
Connection of the PV array grounding kit [optional].
4.
Auxiliary services connection.
5.
Communication accessories connection.
6.
Synchronization connection.
7.
Options connection.
8.
Optional kit connection.
9.
AC connection.
DANGER
Before starting the connection process, press the emergency stop button and keep it interlocked until all the
connections required for the unit to operate correctly have been made.
Do not power the inverter until you have made all the connections and the unit is closed.