Suggested pre-commissioning checklist
Checklist Item
Controller mounting
(According to this document Chapter 2)
Installation of field equipment
According to manufacturer's specification
Labeling
All wires labeled as listed in documentation
Power wiring
Follow local, state and country regulations
End-to-end checks
Voltages, continuity, polarity & destination
Field wiring
All devices checked, all devices switched off
Power availability
Ensure proper line voltage
Visual inspection of controller wiring
Check for AC voltages
Use meter
Check for DC voltages
Use meter
Check for short circuits to earth ground
Use meter
Check for short circuits between terminals
Use meter
* Suggested status codes; X - Completed; NA - Not applicable
98
PHOENIX CONTACT
C 2
Commissioning checklist
As an aid to commissioning a Nanoline, the following tables are provided. These should be
used as a guide to follow during the commissioning process, and to record various setup
and connection data. When completed, the checklists can be kept in the job file. The
checklist will be valuable if changes are required to the system, or for troubleshooting.
For each item, place an X in the Status column, along with your initials and the date
completed. If further work is required, enter that information in the Action column. If desired,
comments can be added for further clarity, such as issues that were fixed or work-arounds.
Action
Completion
Comments
Date
2338_en_O