DLP-G17 Connect Office Power to the ONS 15454 ETSI

Stop. You have completed this procedure.
DLP-G17 Connect Office Power to the ONS 15454 ETSI
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Warning
When installing or replacing the unit, the ground connection must always be made first and disconnected
last. Statement 1046
Caution
Do not apply power to the ONS 15454 ETSI until you complete all installation steps and check the continuity
of the –48 VDC battery and battery return.
Note
No more than 2 m (7 ft) of the power supply cable should be exposed between the equipment and the
fiber-storage tray.
Cisco ONS 15454 Hardware Installation Guide
70
This task connects power to the ONS 15454 ETSI shelf.
#2 Phillips Dynamometric screwdriver
Medium slot-head screwdriver
Small slot-head screwdriver
Wire wrapper
Wire cutters
Wire strippers
Crimp tool
Fuse panel
Power cable (from fuse and alarm panel to assembly), 5.26-mm² (#10 AWG),
copper conductors, 194 degrees F [90 degrees C])
Ground cable 13.3-mm² (#6 AWG) stranded
Listed pressure terminal connectors such as ring and fork types; connectors must
be suitable for 5.26-mm² (#10 AWG) copper conductors
Connect the chassis to the office ground. For detailed instructions on how to
ground the chassis, refer to the
Cisco CPT and Cisco ONS
Platforms.
Required
Onsite
None
Installing the ONS 15454 M12 (ANSI and ETSI) Shelf