DLP-G377 Install the Y-Cable Protection Modules in the Y-Cable Module Tray

Procedure
Step 1
According to the Cisco TransportPlanner Internal Connections Report, determine the Y-cable modules that
you want to install in the FlexLayer shelf.
Step 2
Insert the appropriate Y-cable module into the FlexLayer shelf. Use a Phillips Dynamometric screwdriver to
install the two accompanying screws.
Step 3
Repeat Steps 1 and 2 as necessary for each Y-cable module you want to install. The FlexLayer shelf can hold
up to four Y-cable modules, and the Y-cable tray can hold up to eight Y-cable modules.
Step 4
Return to your originating procedure (NTP).
DLP-G377 Install the Y-Cable Protection Modules in the Y-Cable Module Tray
Purpose
Tools/Equipment
Prerequisite Procedures
Required/As Needed
Onsite/Remote
Security Level
Procedure
Step 1
According to the Cisco TransportPlanner Internal Connections Report, determine which slots you will use to
install the Y-cable modules.
Step 2
Open the drawer of the tray by pushing inward on the latches located at the left and right front of the tray.
Step 3
In the tray, pull up the latches on either side of the module frame and slide the frame upward until it is fully
extended.
Step 4
Line up the first Y-cable module that you want to install with the desired slot, pull the latch at the bottom of
the Y-cable module to enable the Y-cable module to slide onto the guides, and slide the module down until
it is fully installed in the slot. The following figure shows the Y-cable module that can be installed in the
Y-cable module tray.
Cisco ONS 15454 Hardware Installation Guide
130
This task installs the Y-cable protection modules in the Y-cable module tray. The
Y-cable module tray can hold up to eight Y-cable modules.
#2 Phillips Dynamometric screwdriver
Y-cable modules: Multi-Mode Y-Cable Protection Module(s)
(15454-YCM-MM-LC) or Single-Mode Y-Cable Protection Module(s)
(15454-YCM-SM-LC), as appropriate
Cisco TransportPlanner Internal Connections Report