Backing up data and series commissioning
8.5 Write and know-how protection
Commissioning know-how protection
Maintain the following sequence:
1. Check as to whether you must extend the exception list.
2. Activate the know-how protection.
8.5.2.1
Activating and deactivating know-how protection
Activating know-how protection
Preconditions
● The inverter has now been commissioned.
● You have generated the exception list for know-how protection.
● To guarantee know-how protection, you must ensure that the project does not remain at
the end user as a file.
Procedure with STARTER
Proceed as follows to activate know-how protection:
1. Go online with STARTER.
If you have generated a project offline on your computer, you must load the project into
the inverter and go online.
2. Select the required inverter in the project.
3. In the shortcut menu, select "Know-how protection drive unit/activating ....".
192
List of exceptions (Page 195)
Know-how protection (Page 192)
Operating Instructions, 09/2017, FW V4.7 SP9, A5E34257324B AE
SIMATIC ET 200pro FC-2 converter