Power down Core/Net 0

NN43021-461
Standard 06.03
Performing the upgrade
CAUTION — Service Interruption
Service Interruption
Call processing is interrupted for approximately 60
minutes while the procedures are completed.
DANGER OF ELECTRIC SHOCK
In a DC-powered system, power to the column can
remain on during the following procedures. In an
AC-powered system, however, power to the entire
column must be shut down throughout the procedures.
For AC-powered systems: set the MPDU circuit breaker located at the left end
of the module to OFF (down position).
For DC-powered systems: set the breaker for the Core 0 module in the back
of the column pedestal to OFF (down position).
Procedure 29

Removing Core 0 cables and card cage

1
Label and disconnect the Clock Controller 0.
a.
Disconnect the NT8D76AC cable from the Clock Controller 0
faceplate card.
b.
If primary and secondary clock reference cables are connected to the
Clock Controller 0 faceplate, disconnect them last.
2
Label and disconnect all cables from the front of the module.
3
Tape over the contacts to avoid grounding.
4
Tie all cables to the sides so the working area in front of the card cage is
totally clear.
5
Remove the I/O safety panel by turning the screws on each side. Set the
I/O safety panel aside.
6
Tag and disconnect all cables from the backplane to the interior of the
I/O assembly.