Performing the upgrade

Cable Core 1

Table 14
Fanout Panel to 3PE card connectors
Group
Number
0
connects
0
Note: Group 0 cables (NT4N29) connect the fanout panel directly to the network backplane of
Core/Net 1.

Power up Core 1

NN43021-461
Standard 06.03
3
Insert power supply into Core/Net module power supply slot.
In Core 1, inspect the CNI to 3PE (NT4N29) and system monitor
(NT4N89) cables
New NT4N29 cables must be installed for existing Network group 0. If the
system has XSDI cards, reinstall the cards and attach the cables. Inspect the
NT4N89 system monitor cables. See Figure 23 on
Fanout Panel
connector
9-0, J3
from
9-0, J4
Procedure 20
Preparing for power up
1
Check that a terminal is connected to the J25 I/O panel connector
(COM 1) on Core/Net 1.
Note: A maintenance terminal is required to access the Core/Net
modules during the upgrade.
2
Connect a terminal to the J25 port on the I/0 panel in Core 1.
3
Check the terminal settings as follows:
a.
9600 baud
b.
8 data
June 2014
End of Procedure
3PE card connector
to
page 83
and Table 14.