At this point the system reloads and initializes.
Procedure 41
Verifying the upgraded database
1
Print ISSP (system software issue and patches)
LD 22
REQ
****
Core 1 is now active, clock 1 is active CNI is disabled in
Core 0. The system is in split mode.
At this point, Core/Net 0 is ready to be synchronized with Core/Net 1.
Procedure 42
Making the system redundant
1
Hardware enable the CNIs on Core/Net 0.
2
From Core/Net 1, enter LD 135 and issue the JOIN command. The high
speed pipe (HSP) status is now up. This begins the synchronization of the
Cores.
LD 135
JOIN