15. Install the bezel on the enclosure front.
a. Insert the bezel into the enclosure right side.
b. Press in the release tab.
c. Insert the bezel into the enclosure left side.
d. Lock the bezel (optional).
16. Follow the return instructions provided with the replacement component.

Power cooling module or battery replacement

Replace the alternating-current power cooling module battery in a
controller node enclosure—SP 5.x
This procedure is for the replacement of a battery in an alternating-current power cooling module (AC
PCM) of the controller node enclosure using HPE 3PAR Service Processor (SP) 5.x. The battery can be
replaced without replacing the entire PCM.
IMPORTANT:
If both batteries in the power cooling modules in the same controller node enclosure have failed,
only replace one power cooling module battery at a time.
Only one power cooling module can be serviced at a time. If another power cooling module is to
be serviced, verify that the first serviced power cooling module is healthy and functioning, and
then restart this servicing procedure from the beginning for the next power cooling module to be
serviced.
To prevent overheating, the replacement of the power cooling module requires a maximum
service time of six minutes.
Ensure that cables are clear of the power cooling module when installing.
IMPORTANT: Because each battery is a backup for both controller nodes in the controller node
enclosure, controller nodes 0 and 1 both report a problem with a single battery. The Qty appears as
2 in output because two controller nodes are reporting the problem. Battery 0 for controller node 0 is
in the left PCM, and battery 0 for controller node 1 is in the right side PCM (when looking at the
controller node enclosure from the rear).
Prerequisites
Only for the controller node enclosure, verify that at least one PCM Battery in each controller node
enclosure is functional before removing a PCM.
Procedure
Preparation
1.
Unpack the component and place on an ESD safe mat.
2.
Connect to the service processor in the Service Console interface:
Browse to the IP address: https://<sp_ip_address>:8443