Procedure
Connect a cable between a port on a two-port 10Gb Ethernet NIC adapter and the network. To provide
redundancy, connect two or more controller nodes per storage system.
Cabling the power cords of the power distribution units to
the power receptacles at the operating site
IMPORTANT: Do not turn on power to the components at this time. Connect the power cables and
keep the power off until you power on the components.
Each AC power cord on the PDUs must connect to an appropriate outlet based on the cord type and
power requirements for supplying power to the storage system.
Prerequisites
WARNING: Before connecting a main power cable, confirm that the circuit breakers for all internal
PDUs are set to the OFF position to prevent danger of electric shock and potential damage to
equipment.
IMPORTANT: Verify that the operating site provides redundant power.
Procedure
1. Based on the location of the power receptacles at the operating site, route the PDU power cords
through the top or bottom of the rack.
2. Connect the even-numbered PDUs to power receptacles from one power source (source A) and
connect the odd-numbered PDUs to power receptacles from another power source (source B) with
each power receptacle controlled and protected by its own circuit breaker.