Figure 4-5. Section Joining - Eaton Powerware 9395 UPS 10001100 kVA Installation And Operation Manual

1000–1100 kva
Table of Contents

Advertisement

UPS SYSTEM INSTALLATION
Left Top Panel
Left Middle Panel
Interior Left
Side Panel
Corner Channel
4−6
EATON Powerware

Figure 4-5. Section Joining

5.
Remove the screws securing the left top panel and remove the panel (see
Figure 4-5). Retain the hardware for later use.
6.
Remove the screws securing the left middle panel and remove the panel (see
Figure 4-5). Retain the hardware for later use.
Use care during installation to protect components mounted on the right side of the ISBM section and the
intercabinet wiring harnesses attached to the left side UPM section from damage.
NOTE Clearance between the ISBM and the UPM sections must be less than 1/2" so that joining brackets
can be installed.
7.
Using a forklift with the forks in the front forklift slots, position the ISBM section
adjacent to the left side of the previously installed UPM section. Verify that the
ISBM section right side is against the UPM section left side and the front of the
cabinet bases are flush with each other (see Figure 4-6).
8.
Reinstall the corner channel (see Figure 4-5) and secure using the retained
hardware.
9.
Reinstall the left middle panel (see Figure 4-5) and secure using the retained
hardware.
®
9395 UPS (1000–1100 kVA) Installation and Operation Manual
UPM Section
Wireway Panel
C A U T I O N
S
164201764 Rev 1 www.powerware.com

Advertisement

Table of Contents
loading

This manual is also suitable for:

Powerware 9395

Table of Contents