NOTE Two cable lugs will be connected to each terminal stud. When connecting the cable lugs, install the
first lug on the stud with the raised barrel portion facing the back of the cabinet. Install the second lug with
the raised barrel portion facing the front of the cabinet.
6.
7.
NOTE In Step 8, route the wiring harnesses in the area as shown in Figure 4-8 on page 4−11 to provide
operating clearance for the bypass breaker CB4 charging handle.
8.
NOTE When connecting the UPM battery cables, verify the cables are connected to the correct terminals .
9.
NOTE AC output intercabinet power wiring harnesses are supplied attached to the interior left side panel
of the UPM section (see Figure 4-5 on page 4−6).
10. Locate the 1G4, 1G5, 2G4, 2G5, 3G4, and 3G5 power wiring harnesses. Remove
NOTE Two cable lugs will be connected to each terminal stud. When connecting the cable lugs, install the
first lug on the stud with the raised barrel portion facing the back of the cabinet. Install the second lug with
the raised barrel portion facing the front of the cabinet.
11. Using hardware from the intercabinet wiring terminal hardware kit (see
12. Install the remaining hardware (three washers, conical washers, and nuts) onto
EATON Powerware
®
9395 UPS (1000–1100 kVA) Installation and Operation Manual
Locate the intercabinet wiring terminal hardware kit packed on the bottom right
side of the ISBM section.
Using hardware from the intercabinet wiring terminal hardware kit (see Table 3-9
on page 3−13), connect phase A, B, and C cable lug connections to the AC Input
to UPMs terminals. Follow the callout details in Figure 4-9 on page 4−12 to
connect the correct cable lug to the proper terminals. See paragraph 3.2.2 on
page 3−8 for wiring and termination requirements.
Locate the 1G3, 2G3, and 3G3 power wiring harnesses. Route these harnesses
through the wiring access in the right side panel of the ISBM section to the DC
Input to UPMs terminals. See Figure 4-8 on page 4−11 for terminal locations.
Using hardware from the intercabinet wiring terminal hardware kit (see
Table 3-9), connect the positive and negative cable lug connections to the DC
Input to UPMs terminals. Follow the callout details in Figure 4-10 on page 4−13 to
connect the correct cable lug to the proper terminals. See paragraph 3.2.2 on
page 3−8 for wiring and termination requirements.
the front two columns of wire ties securing the cables to facilitate routing cables
to the AC Output from UPMs terminals. See Figure 4-8 on page 4−11 for terminal
locations.
Table 3-9), connect phase A, B, and C and Neutral cable lug connections to the
AC Output from UPMs terminals. Follow the callout details in Figure 4-11 on
page 4−13 to connect the correct cable lug to the proper terminals. See
paragraph 3.2.2 on page 3−8 for wiring and termination requirements.
the AC Input to UPMs terminals designated for the four UPM model and secure
the hardware (see Figure 4-9 on page 4−12). This hardware is used by an Eaton
Customer Service Engineer to install a Field Installed UPM (FI−UPM).