NOTE If the load requires a neutral, a bypass source neutral must be provided. If the load does not require a neutral and there is no neutral conductor
connected at the bypass input, a neutral to ground bonding jumper must be installed. DO NOT install both a source neutral and a bonding jumper.
6−10
EATON Powerware
AC Input to
AC Input to
Bypass
3 or 4 Wire A−B−C
Rotation
Rotation
B
A
E6, E7,
E8, E12
Fuse
Input
Contactor
(K1)
Rectifier
Fuse
Fuse
Fuse
Inverter
Output
Contactor
(K3)
Battery
Converter
Fuse
Battery Contactor (K2)
UPM 1
E4. E5
C
Battery
Breaker
BATTERY SYSTEM
(Not supplied with the UPS)
D
map to Table 3-5 on page 3−10.
Figure 6-8. Three UPM UPS System, Dual-Feed, Separate Battery System
®