Mounting and Commissioning
This chapter is intended for experienced commissioning staff. He must be familiar with the commissioning of
protection and control systems, the management of power systems and the safety rules and regulations. Hard-
ware adjustments to the power system data might be necessary. The primary tests require the protected object
(line, transformer, etc.) to carry load.
3.1
Mounting and Connections
3.2
Checking Connections
3.3
Commissioning
3.4
Final Preparation of the Device
SIPROTEC, 7SJ62/64, Manual
C53000-G1140-C207-2, Release date 01.2008
3
392
438
443
463
391