Commissioning Notes - Siemens Reyrolle 7SR45 Argus Device Manual

Hide thumbs Also See for Reyrolle 7SR45 Argus:
Table of Contents

Advertisement

Functional Tests

6.1 Commissioning Notes

6.1
Commissioning Notes
Overview
The commissioning tests are carried out to prove the following:
The relay is not damaged in transit.
The relay is correctly connected and installed.
The characteristics of the protection and settings which are based on calculations.
Settings are correctly applied.
Obtain a set of test results for future reference.
104
Reyrolle, 7SR45, Device Manual
C53000-G7040-C101-2, Edition 09.2020