Functional Tests
6.1 Commissioning Notes
6.1
Commissioning Notes
Overview
The commissioning tests are carried out to prove the following:
•
The relay is not damaged in transit.
•
The relay is correctly connected and installed.
•
The characteristics of the protection and settings which are based on calculations.
•
Settings are correctly applied.
•
Obtain a set of test results for future reference.
104
Reyrolle, 7SR45, Device Manual
C53000-G7040-C101-2, Edition 09.2020