Specifying the setpoint via the fieldbus
Interconnecting the fieldbus with the main setpoint
Image 6-22
Most standard telegrams receive the speed setpoint as a second process data PZD2.
Table 6- 20
Parameter
p1070 = 2050[1]
p1075 = 2050[1]
Converter with the CU240B-2 and CU240E-2 Control Units
Operating Instructions, 01/2016, FW V4.7 SP6, A5E34259001B AC
Fieldbus as setpoint source
Setting the fieldbus as setpoint source
Remark
Main setpoint
Interconnect the main setpoint with process data PZD2 from the fieldbus.
Additional setpoint
Interconnect the additional setpoint with process data PZD2 from the fieldbus.
Advanced commissioning
6.3 Setpoints