Checking The Project Data And Os Writing On Got - Mitsubishi Electric GOT2000 Series Connection Manual

Graphic operation terminal
Hide thumbs Also See for GOT2000 Series:
Table of Contents

Advertisement

1.2.2

Checking the project data and OS writing on GOT

Confirm if the standard monitor OS, communication driver, option OS, project data and communication settings are
properly written onto the GOT by reading from GOT using GT Designer3.
For reading from the GOT, refer to the following manual.
GT Designer3 (GOT2000) Help
1.
Select [Communication]
2.
The [Communication configuration] dialog box appears.
Set the communication setting between the GOT and the personal computer.
Click the [OK] button when settings are completed.
3.
The [GOT Read] tab appears on the [Communicate with GOT] dialog box.
Select the [Drive information] radio button of the Read Data.
4.
Click the [Info Reception] button.
5.
Confirm that the project data and OS are written correctly onto the GOT.
[Read from GOT...] from the menu.
1. PREPARATORY PROCEDURES FOR MONITORING
1.2 Writing the Project Data and OS onto the GOT
1
1 - 13

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents