Preassembled System Installation; Inspecting The Equipment; Tools Required - Eaton bladeups User Manual

Eaton bladeups 12 kva to 60 kva (n+1) systems
Hide thumbs Also See for bladeups:
Table of Contents

Advertisement

Chapter 3

Preassembled System Installation

The preassembled system comes with the BladeUPS Bar, wireway, and BladeUPS modules already installed.
For five and six UPS systems, some batteries are shipped uninstalled for better weight distribution.
This chapter explains:
Equipment inspection
l

Tools required

l
Floor loading
l
Unwrapping the system
l
Unloading the system
l
Preassembled system setup
l
Installing the input and output wiring
l
Installing UPS internal batteries
l
Extended Battery Module (EBM) setup and installation (optional)
l
Initial startup
l

Inspecting the Equipment

If any equipment has been damaged during shipment, keep the shipping cartons and packing materials for the
carrier or place of purchase, and file a claim for shipping damage. If you discover damage after acceptance, file
a claim for concealed damage.
To file a claim for shipping damage or concealed damage: 1) File with the carrier within 15 days of receipt of the
equipment; 2) Send a copy of the damage claim within 15 days to your service representative.
Tools Required
To assemble the components, you may need the following tools:
Medium flat-bladed screwdriver
l
Short-handled #2 Phillips
l
Long-handled #2 Phillips screwdriver
l
7 and 8 mm wrench or socket
l
14 mm wrench or socket
l
Utility knife
l
Adjustable pliers
l
NOTE
For instructions on how to install the optional Maintenance Bypass Module (MBM),
refer to the user's guide for the MBM.
®
screwdriver
Eaton BladeUPS 12 kVA to 60 kVA (N+1) User's Guide 164201649—Rev 7