Blue Terminating Plug (CAN IN)
Figure 65. Installing the Blue Terminating Plug (Single Parallel-Ready UPS Installation)
9.
Tighten the screws securing the Powerware Hot Sync CAN Bridge Card in its X-Slot communication bay.
10. If you are installing power management software, connect your computer to the UPS communication port
or optional X-Slot card (see page 107). For the communication port, use the supplied serial cable.
NOTE
You can install one ConnectUPS-X Web/SNMP Card per UPS, or one card per
parallel system. Installing one card per UPS provides communication with each
UPS. Installing one card per parallel system provides detection of a problem with at
least one UPS, but does not specify which UPS or how many.
11. If you left the UPS unattached to the rack, secure the front and rear of the UPS as described in Steps 14
and 15 on page 63.
12. If your rack has conductors for grounding or bonding of ungrounded metal parts, connect the ground cable
(not included) to the ground bonding screw. See Figure 59 on page 70 for the location of the ground
bonding screw.
13. You can install an optional REPO circuit that will shut down the entire parallel-ready system using a single
switch. See "Remote Emergency Power-off" on page 113 to install the REPO switch before powering on
the parallel-ready system.
Eaton BladeUPS 12 kVA to 60 kVA (N+1) User's Guide 164201649—Rev 7
Standard System Installation
Blue Terminating Plug (CAN OUT)
79