Standard System Installation

Installing the UPS Internal Batteries

The UPS internal batteries are heavy (see page 130). Each battery tray holds two rows of five
batteries. Use caution when handling the heavy battery trays.
To install the battery trays into the UPS cabinet:
1.
Verify that the circuit breakers on the UPS rear panel are in the OFF (O) position (see Figure 59 on
page 70).
2.
Remove the eight screws on the battery cover plate and retain. Remove the plate and retain. See
Figure 53.
Figure 53. Removing the UPS Battery Cover Plate
3.
Slide the battery trays into the cabinet (see Figure 54). Verify that each tray is properly aligned before
sliding the tray in.
When a tray is fully installed, tuck the plastic handle on the end of the tray into place.
Figure 54. Installing the UPS Battery Trays
4.
Reinstall the battery cover plate.