Mounting a QFX5100 Device in a Rack or Cabinet

Before You Begin Rack Installation

160
If you are using the QFX5100 device as a Node device in a QFX3000-M QFabric
system, see QFX3000-M QFabric System Installation Overview for information about
the steps to install and configure your QFX3000-M QFabric system.
If you are using a QFX5100-24Q as an Interconnect device in a QFX3000-M QFabric
system, see Connecting a QFX5100 Node Device to a QFX5100-24Q Interconnect
Device.
If you are using the QFX5100 device in a Virtual Chassis Fabric, see
QFX5100 Device in a Virtual Chassis Fabric" on page
Rack Requirements for a QFX5100 Device on page 74
Cabinet Requirements for a QFX5100 Device on page 75
Clearance Requirements for Airflow and Hardware Maintenance for a QFX5100 Device
on page 76
You can mount all QFX5100 switches on a four post 19-in. rack or cabinet using the
mounting kit provided with the device.
For four post rack or cabinet installations, the mounting kit contains two front mounting
rails with two matching rear mounting blades. This configuration allows either end of the
switch to be mounted flush with the rack and still be adjustable for racks with different
depths.
The mounting kit for the QFX5100-96S has mounting rails, blades, and brackets for the
four-post configuration.
(The remainder of this topic uses "rack" to mean "rack or cabinet.") The front and rear
rack rails must be spaced between 28 in. (71.1 cm) and 36 in. (91.4 cm) front to back.
This topic describes:
Before You Begin Rack Installation on page 160
Four-Post Procedure on page 162
Two -Post Procedure on page 164
Before you begin mounting a QFX5100 switch in the rack or cabinet:
Ensure that you understand how to prevent electrostatic discharge (ESD) damage.
1.
See
"Prevention of Electrostatic Discharge Damage" on page
Verify that the site meets the requirements described in
2.
for a QFX5100 Device" on page
Place the rack in its permanent location, allowing adequate clearance for airflow and
3.
maintenance, and secure it to the building structure.
187.
"Site Preparation Checklist
67.
Copyright © 2016, Juniper Networks, Inc.
"Connecting a