Wire addle
Figure 54. Installing the Communication Terminal Block Connectors
20. Continue to the "Installing the UPS Internal Batteries" section.
Installing the UPS Internal Batteries
The UPS internal batteries are heavy (see page 136). Each battery tray holds two rows of five
batteries. Use caution when handling the heavy battery trays.
To install the battery trays into the UPS cabinet:
1.
Verify that the circuit breakers on the UPS rear panel are in the OFF (O) position (see Figure 60 on
page 74).
2.
Remove the eight screws on the battery cover plate and retain. Remove the plate and retain. See
Figure 55.
Figure 55. Removing the UPS Battery Cover Plate
Eaton BladeUPS 5.1 kVA to 60 kVA (N+1) User's Guide 164201649—Rev 9 www.eaton.com/powerquality
Wire addle
2-Pin Connector
2-Pin Connector
2-Pin with Jumper
2-Pin Connector
2-Pin with Jumper
3-Pin Connector
CAUTION
Standard System Installation
69