6.
Wait for the front panel display on each UPS to illuminate.
The
indicator flashes on each UPS.
7 .
Check each UPS front panel display for active alarms or notices (other than "Batteries Disconnected").
Resolve any active alarms before continuing (see "Troubleshooting" on page 135).
8.
Switch all UPS battery circuit breakers to the ON (
9.
If optional EBMs are installed, switch all EBM battery circuit breakers to the ON (
10. Verify that the "Batteries Disconnected" alarm on each UPS has cleared. Verify that no other alarms
appear on any UPS front panel display.
If the
indicator is flashing on any UPS, do not proceed until all alarms are clear. Check the UPS status
from the front panel to view the active alarms. Correct the alarms and restart if necessary.
11. On any UPS, press any button on the front panel display to activate the menu options. Select TURN UPS
ON/OFF and TURN SYSTEM ON.
12. Confirm the selection. Press and hold the
Verify that the
indicator illuminates solid on each UPS, indicating that the UPS is operating normally
and any loads not connected through the Load Connector are now energized.
If the
indicator on any UPS is flashing, do not proceed until all alarms are clear. Check the UPS status
from the front panel to view the active alarms. Correct the alarms and restart if necessary.
Each UPS should be in Normal mode. By default, Normal mode operates on the High Efficiency setting
(see "Normal Mode" on page 97.
13. To energize loads connected through the Load Connectors, switch all load connector circuit breakers to

the ON (
) position.
14. On any UPS, press the

Starting the UPS on Internal Bypass

NOTE
Starting the UPS on internal bypass leaves the load unprotected.
To start a standalone UPS on internal bypass (see Figure 60 on page 74):
1.
Verify that all UPS circuit breakers are in the OFF (O) position.
NOTE
The load connector breaker controls the load connector only, not the output power
cord.
2.
Verify that the UPS power cord is plugged in.
3.
Verify that all UPS power cords are plugged in and secured by the plug retainers (see Figure 65 on
page 81).
4.
Switch on utility power where the UPS is connected.
5.
Switch the UPS input circuit breaker to the ON (
6.
Wait for the UPS front panel display to illuminate.
The
indicator flashes on the UPS.
Eaton BladeUPS 5.1 kVA to 60 kVA (N+1) User's Guide 164201649—Rev 9 www.eaton.com/powerquality

button for three seconds, until the UPS stops beeping.
ESC
button until the Start screen appears.
