INSTALLATION
26
®
Eaton
9140 (9910-E82/E83) UPS Installation Guide for IBM
www.eaton.com/ibm

Installing the UPS Internal Batteries

To install the battery trays into the UPS cabinet (located in the cartons
labeled 9910-E82/E83-6646 Battery Tray, PN 44V3920):
1.
Verify that the output circuit breakers on the UPS rear panel are in
the OFF (O) position (see Figure 25 on page 28).
2.
Slide the battery trays into the cabinet (see Figure 23). Push each
tray in until the battery tray lock on the handle catches to lock the
tray in place.
3.
Replace the UPS front cover and tighten the two front cover screws
(see Figure 24).
Figure 24. Replacing the UPS Front Cover
4.
If you are installing an optional EBM, continue to the following
section, "EBM Installation." Otherwise, continue to "UPS
Installation" on page 29.
Figure 23. Installing the Battery Trays