Eaton BladeUPS User Manual page 52

For use with eaton bladeups 5 kva to 60 kva (n+1) systems
Hide thumbs Also See for BladeUPS:
Table of Contents

Advertisement

2.
Select the proper holes in the rail for positioning the EBMs in the rack.
Place the first rail for the first EBM above the UPS, using positions 37 and 42 for the front hex-head
screws. If you are installing additional rails, place the next rail 4 holes above the last installed screw (see
Figure 32).
NOTE
Verify that the hole patterns on the rails and mounting brackets align with the hole
pattern on the rack.
Position 51
Position 46
Position 42
Position 37
UPS
Wireway
Bottom of Rack
Front Rail Screw Positions
Figure 32. Rail Screw Positions for the EBM (Single UPS and Parallel Wireway with Two EBMs Shown)
Eaton BladeUPS 5.1 kVA to 60 kVA (N+1) User's Guide 164201649—Rev 9 www.eaton.com/powerquality
econd Rail
First Rail
Bottom of Rack
Rear Rail Screw Positions
Preassembled System Installation
Position 49
econd Rail
Position 47
Position 40
First Rail
Position 38
UPS
Wireway
45