10. Install the second supplied blue terminating plug (see Figure 63) into the CAN OUT port on the last UPS
(UPS 3 in Figure 64).
Blue Terminating Plug (CAN OUT)
Figure 63. Installing the Blue Terminating Plug (Last UPS)
11. Verify that only the first and last UPSs in the configuration have a blue terminating plug installed.
12. Using the supplied connectors, install a CAN Bridge Card cable between each UPS as shown in Figure 64,
connecting the CAN OUT port on one UPS to the CAN IN port on the next UPS.
On startup, the parallel system will identify the UPS wired after UNIT 1 as UNIT 2, and so forth.
NOTE
You can configure the parallel system with UPS 1 at the bottom of the rack (as
shown in Figure 64) or at the top of the rack.
Eaton BladeUPS 5.1 kVA to 60 kVA (N+1) User's Guide 164201649—Rev 9 www.eaton.com/powerquality
Standard System Installation
78